RAID Log: Template and Example for Project Managers

The four letters, the columns, a pre-mortem to fill it, and the two risks a software team knew about but had never written down.

Updated 24 September 2026 · 7 min read · By a former Gartner Managing Partner

The short answer

A RAID log is one table that tracks a project’s Risks, Assumptions, Issues and Dependencies. Each entry gets a score (probability × impact, each out of 5), a trigger that shows it is happening, one owner and a response. Fill it with a pre-mortem: imagine the project has already failed and list why. Review it weekly, and show leadership only the top five.

What the four letters mean

LetterWhat it isExample
RiskSomething that may happen and would hurt the projectThe one engineer who knows a system leaves
AssumptionSomething the plan treats as true but nobody has confirmedCustomers accept a signature captured offline
IssueA risk that has already happenedA key component is nine days late
DependencySomething the project needs from outside the teamApp store review before release

The log puts all four in one place because they turn into each other. An unconfirmed assumption is a risk; a risk that happens becomes an issue; a dependency that is late becomes an issue on the critical path.

The columns of a RAID log

ColumnWhat goes in it
IDR1, A1, I1, D1, so entries can be referred to in meetings
EntryWritten as cause and effect: “Because X, Y may happen”
ScoreProbability (1–5) × impact (1–5), so 1 to 25
TriggerThe observable sign that the risk is happening
OwnerOne named role, not “the team”
ResponseAvoid, mitigate, transfer or accept, with its cost
Review dateWhen it is next checked

The four standard responses: avoid (change the plan so the risk cannot happen), mitigate (reduce its probability or impact), transfer (move it to someone else, such as an insurer or a supplier) and accept (do nothing, and plan for the impact). Every response except accept has a cost, and the log should state it.

How to build one in six steps

1. Run a pre-mortem

Gather the team and say: “It is six months from now and the project has failed. Write down why.” People name risks as causes of a failure far more readily than they predict them, and the risks they already know about but have never said aloud come out.

2. Sort each item into R, A, I or D

Rewrite each as cause and effect. “Priya” is not a risk; “Because one engineer wrote the sync layer, her leaving would stop the critical path” is.

3. Score probability and impact

Score each from 1 to 5 and multiply. A common rule: a score of 12 or more needs a costed response and an owner this week; under 6 is usually accepted and monitored.

4. Name a trigger for each high score

A trigger turns a worry into something checkable: “fewer than 4 of 5 pilot accounts confirmed by 15 January”.

5. Give each one owner and a costed response

Compare the cost of the response with the cost of the risk happening. If the response costs more, accept the risk and say so.

6. Review weekly, report the top five

Rescore every entry weekly. Leadership sees the five highest scores with their owners, not the whole log.

Worked example: Corbel

The scenario

A board promise, 14 engineers and a release that shipped 11 weeks late

Corbel sells scheduling and dispatch software to heating, air-conditioning and plumbing contractors, with $31 million of annual revenue. Its last major release shipped 11 weeks late and 38% over budget. Now the CEO has told the board that technicians will be able to work offline by the end of Q1 2027.

23entries from one pre-mortem
20top risk score: 4 × 5
6 vs 8engineer-weeks to mitigate, against weeks of standstill

The pre-mortem produced 23 entries: 14 risks, 5 assumptions, 2 issues and 2 dependencies. The two highest scores came from things the team knew but had never written down: one came from a tech lead’s one-to-one, the other from a calendar.

IDEntryScoreTriggerOwner and response
R1Because one engineer wrote the sync layer, her leaving would stop the critical path20Any sync change reviewed by her aloneEngineering lead: pair a second engineer from week 2
R2Because the pilot falls in the heating season, pilot accounts may not give it time16Fewer than 4 of 5 accounts confirmed by 15 JanHead of customer success: recruit 8 accounts, 3 of them plumbing contractors
R3Because iOS limits background activity, jobs may not sync until the app is reopened15Background sync test fails beyond 10 minutesiOS lead: sync on reopen, tested on 4 iOS versions by week 6
A1Contractors accept a signature captured offline as proof of completionConfirm with 5 accounts by 30 NovHead of product: validate in pilot contracts
D1Apple and Google app store review, 5 to 10 daysSubmission not ready by 1 Mar 2027Release manager: on the critical path

R1 shows why each response carries a cost. Pairing a second engineer on the sync layer from week 2 costs 6 engineer-weeks. If Priya left without that cover, the critical path would stand still for about 8 weeks while a replacement learned the system. The response costs less than the risk, so it goes ahead.

R2 came from the calendar. Commercial heating contractors are at full stretch in January and February, exactly when the pilot was scheduled. The response recruits eight pilot accounts instead of five, so the pilot survives if three are too busy.

What a one-line prompt gets wrong

Where it goes wrongWhat usually comes backWhat the log needs
ContentGeneric risks: “scope creep”, “resource constraints”This project’s risks, from a pre-mortem
WordingSingle nounsCause and effect
ScoresHigh, medium, lowProbability × impact, 1 to 25
Owners“Project team”One named role each
Responses“Monitor closely”Avoid, mitigate, transfer or accept, with the cost

Try it: a shortened Prompt 07

This is a shortened version of Prompt 07 from the Product & Project Management pack, set up to run on its own. Paste it into ChatGPT, Claude or Gemini and fill in the brackets.

A shortened version of Prompt 07, RAID Log & Pre-mortem, from the Product & Project Management pack
You are a former programme director who has run software and operations projects through board-level review. The risks that sink a project are usually known to someone on the team and never written down, so you run a pre-mortem first and score every entry, instead of listing generic project risks.

THE PROJECT:
- What it delivers and by when: [scope, deadline, who promised it to whom]
- Team and budget: [people, key skills, budget]
- The plan's main phases and the critical path: [phases, dates]

WHAT THE TEAM KNOWS:
- Concerns people have raised, even informally: [paste notes, one-to-one comments]
- Outside dependencies: [suppliers, approvals, other teams, app stores, customers]
- What went wrong on the last similar project: [if known]

Produce:

1. THE PRE-MORTEM. Assume the project has failed. The ten most likely reasons, each written as cause and effect.

2. THE RAID LOG. Every entry sorted into risk, assumption, issue or dependency, with ID, probability (1-5), impact (1-5), score, trigger and one owner.

3. THE RESPONSES. For every risk scoring 12 or more: avoid, mitigate, transfer or accept, with the cost of the response against the cost of the risk.

4. THE TOP FIVE. The five entries leadership should see, in one table.

Use only what I tell you about this project. Where an entry rests on your judgement rather than my input, mark it [TO CONFIRM].

The full Prompt 07 has eight parts rather than four, and it reads the Initiative Brief built by prompts 01 to 06, so the pre-mortem is run against the actual business case, requirements and critical path.

Checks before the review

Questions

What does RAID stand for?

Risks, assumptions, issues and dependencies. Some teams use D for decisions instead of dependencies; use whichever your organisation already reviews, and keep all four in one log.

What is the difference between a risk and an issue?

A risk may happen; an issue has happened. When a risk’s trigger fires, it moves to the issues section with an action and a date.

How do you score a risk?

Rate its probability and its impact from 1 to 5 and multiply them, giving a score from 1 to 25. Agree what each number means before scoring, so two people give the same risk the same score.

What is a pre-mortem?

A session in which the team imagines the project has already failed and lists the reasons. It surfaces risks people are reluctant to raise when asked to predict problems directly.

Written by a former Gartner Managing Partner and investment banking SVP

The guides and the prompt templates on this site come from a career spent building these documents: board decks, forecasts, business cases and hiring decisions, as Managing Partner at Gartner, SVP in investment banking and Country Manager at international subsidiaries. The worked examples are published in full on each product page. Browse the Prompt Library.

Corbel and the people named are fictional, and the figures are illustrative.

Output from any AI tool should be reviewed before use.